PHOTO RECORD / FACT
Fire detection
EL-028 / FIRE DETECTION / CABLE LINE FIXING
PRIORITY / MAJOR
OBSERVED
The material used to secure the fire alarm cable lines differs from that specified in the local cost estimate.
RISK
The actual installation differs from the agreed scope of work and materials. Without further checks, compliance of the fixing with the design requirements and requirements for this cable line cannot be confirmed.
WHAT TO CHECK
The working documentation, local cost estimate, material actually used, and specified method of fixing the fire alarm cable lines.
RECOMMENDED ACTION
Compare the actual fixing with the working documentation and local cost estimate. If no substitution has been agreed, bring the installation into compliance with the approved solution or document the change under the project’s established procedure.
PRIORITY / MAJOR